We thought about doing it ourselves. Between our light bathroom remodeling experience in our old house and YouTube, we probably could have. However, with the kids all on different school schedules, Paul traveling one week out of the month and curling, swimming and other activities we figured we did not have the amount of uninterrupted time for our basic home improvement skills to finish it properly. So we had 4 contractors who were all recommended come and make bids.
2 were pretty pricey, 2 were lower and one of those two was optimistic that he could even possibly have at least the shower put in by the time my parents were scheduled to come see the house for the first time, so we hired him.
Things started out well and Erin got shopping (not paying for that-- I've got awesome skills in that department). Then the floor tiles started cracking. The contractor told us that the tiles the previous homeowner had left that worked just fine on the shower walls were too cheap and we needed to go get new ones. With our limited experience, we were skeptical and thought it had more to do with the installation, but bought some one grade higher and they spent 2 days chipping the floor out that they'd spent 2 days on. Paul did an awesome job finding just enough boxes of instock tile that really matched almost perfectly to the tile already on the walls. Needless to say it didn't get done in time for my parent's visit. Because they had to redo the work, we compromised on not having them also tile the laundry room. We also told him we were doing our own painting which knocked $400 off the bid.
My honest review: While I'm happy it's done and know that paying someone to do it means the job was done a year before we normally would have had time to devote to the project, I will not be hiring this particular contractor again. I think my initial disappointment was that the quality was what I probably could have done myself if I'd had enough long spurts of time available to work on the job and if I'm paying for it to be done I want it better than I could have done it. They were over budget on time and while they'd work Monday through Saturday, some days they'd leave at 1pm, some days we'd peek in and think, WTH did they do all day? The bathroom and laundry room were also FILTHY when they left. I told Paul I would have been much happier with the job if they'd just spent some extra time cleaning up. Instead I did it and I noticed every higher tile, the 2 that were cracked and every other little thing that I never would have seen when I was awed by the job but that I noticed right away because my face was 6 inches from it cleaning. I spent 2 days cleaning and painting. By 2 days I mean long days. NOW that I've cleaned and painted it I'm quite happy with it. Now that I'm using it I'm happy with it. But I asked Paul to stop asking me how I liked it most of last weekend ;) Today we also changed to a tankless hot water heater so I now have an extra 4x4 foot area in my furnace room for storage.
Here's the end result...
The view from the bathroom door into my laundry room pocket door. Before putting in the pocket door, the door opening was to the right, in the corner, which meant you had to walk around the vanity, this is a much better flow.
To the right... I now have a corner to put my freezer in and storage for cleaning supplies. I'm keeping them in the bins until I move out the shelves to tile in there, then I'll organize it.
To the left, my laundry tub, laundry machines and pantry storage above. I took these shelves out of the garage and reused them to add some pantry space to our smaller kitchen. the tank water heater has been replaced with a tankless which is attached to the wall so that back corner is now all free space.
Looking into the bathroom with the pocket door closed, the other door is a linen closet, vanity to right, toilet to left.
New vanity and mirror with extra space in the corner for a plant, shelves.....??? The lights and mirror seem a little low because there's ductwork above the vanity area, good thing we're a short family
The toilet and new shower and his and hers towel bars. Both windows have a contact paper that's a privacy screen. Easily installed with an exacto knife and a squeegee.
The shower. Shower bar with jets and rain shower, niche cut in between the studs with glass shelf-big enough for Costco sized shampoo, the window in there is also tiled so you can put stuff up there as well. Doors are Maax Halo 60 inch doors. Shower is 5'x5' with center drain. Gray tile line is same tile that's on the floor.
What does this all cost? Here's the breakdown, including tax (13.5% here)
| Labor & construction supplies (except cleaning & painting) | 5,650.00 |
| Door Knobs-privacy & closet | 65.52 |
| Molding & Shelving, Baseboards | 132.60 |
| Towel holders, TP holder | 135.66 |
| Faucet | 122.04 |
| Tile (bathroom and laundry) | 271.38 |
| Shower body bar-$150 off sale | 449.74 |
| Vanity & sink top-48 inch marked off $60 for scratches down by the floor | 847.67 |
| Vanity light | 90.40 |
| Pocket Door-primed | 153.67 |
| Paint-1 gal midgrade Benjamin Moore & 1 quart Zinnzer for molding & doors | 70.00 |
| Shower doors | 733.37 |
| Mirror | 33.90 |
| Accessories | 32.70 |
| 8,788.66 |